Natal Government Railways carriage NG29

History

NG29 was built in Darnall in 1910 by Cravens of Staniforth Road, less than 1/2 a mile from the Trust’s workshops, for Natal Government Railways in South Africa. There was previously some discussion about the builder of the carriage but recently the quality control inspector’s marks have been found on the chassis proving beyond doubt where and when it was manufactured.

A Cravens advert promoting their products. Much of their output was exported, giving service all around the world.

NG29 was built to type NG. N-2 for the Mid-Illovo & Alfred County Railway. As designed it was an ornately furnished and very comfortable coach with seating for 15 “European” 1st Class passengers in two compartments with facing bench seats and one coupe half compartment with observation windows in the end. Just over a third of the length was devoted to the van area, handbrake and guard’s accomodation. It rode on Fox’s Patent die stamped bogies with leaf springs.

Passengers were provided with drop light windows paired with drop shutters made of slatted wood for shade and ventilation with the windows open.

This wonderful drawing shows NG29 as it would have been when brand new. Note the seperate compartments.
Pre-eminent South African Railways historian Leith Paxton drew this diagram of NG29 in its original form as type NG. N-2.

Decor was to the standard of the larger Cape gauge (3’6″) stock built at the same time, and even included cut glass partitions engraved with the Natal Government Railways logo.

Cravens Ltd drawing showing the design for the cut glass partitions used in 2.0′ gauge stock.

Later in South African Railways service it was rebuilt to type NG.N-6 with an open saloon that provided reduced 1st class seating for 9 passengers, a toilet in an end compartment and a large guard’s van with handbrake, vacuum gauge and setter. It didn’t get the end doors of the earlier Cravens vans so the toilet could only be used by NG29’s passengers.

NG29’s South African Railways staff information diagram after rebuild.
NG29 in SAR livery.

We don’t have a huge amount of information about NG29’s life in service but it appears to have been quite uneventful barring occasional overhauls. After its rebuild to an open carriage the only other significant modification appears to have been the over plating of the matchboard lower sides with metal sheets. This is a common modification on SAR narrow gauge carriages to extend their life.

Later in its service life NG29 was repainted into all over Green livery, and it carried this until the end of its career.

NG29 in fresh green paint showng the metal plated lower sides and paneled in compartment windows at the far end which were installed when it was converted to a toilet.

Eventually NG29 was withdrawn from use and dumped at Port Shepstone where spare part removal, weather and vandalism eventually took its toll.

NG29 dumped at Port Shepstone

Fortunately this wasn’t the end for NG29. Eventually it was rescued by Sandstone Estates who moved it to their base near Ficksburg in the Orange Free State. Whilst there the remains of the wooden body were removed but restoration didn’t get much further due to other projects. In 2022 Sandstone kindly transferred ownership of NG29 to the DLRHT so it could be returned home for restoration.

NG29 at Sandstone Estates in South Africa.

Arrival back in the UK

NG29 arrived in the UK in 2023 as part of a larger shipment, initially being unloaded at the Bala Lake Railway in Llanuwchllyn, North Wales, before transport to the trust’s Sheffield base. The chassis has been sand blasted and painted, and is currently waiting for floor space in the main erecting shop for welded and riveted corrosion repairs to begin.

The bogies were stripped on arrival and sand blasted. New springs are on order from Owen Springs in Rotherham, and the wheels and axleboxes are currently awaiting transport to Boston Lodge Works on the Ffestiniog Railway for tyre turning and re-metalling.

The Boston Lodge’s quote for the repair of the body has been accepted and the chassis will leave for Wales to join the carriage works queue when its repair is complete.

Restoration

28th July 2026

Painting of minor parts removed from the chassis is ongoing. Seen here balanced on the regulator quadrant from NG15 120 is one of the bogie retaining chain brackets receiving a coat of gloss black.

27th January 2026

The centre and right side Coupé end gussets are now installed and await welding. The corroded wear plate has been removed from the drawbar hole. Some more measuring needs to be done before the new drawbar assemblies are ordered.

15th January 2026

The centre gusset at the Coupé end of NG29 is now installed with temporary bolts. The right side one needs some further work before installation.

6th January 2026

Two of the three gussets at the Coupé end of NG29’s chassis have been drilled ready for rivetting. They will be painted underneath before being installed with temporary bolts. Placing the holes accurately from below is a bit of a pain, but once one has been done it can be copied for the others of the same type.

4th November 2025

The test piece and first of the 20 foot board brackets has been forged in our workshop. The technique neeeds a little refinement but it is very pleasing to have started on what is quite a challenging task.

3rd November 2025

NG29’s surviving draw bar has been extracted, which will allow the final measurements to be taken for replacement parts to be manufactured. This work is being outsourced. Rivet removal on corroded parts continues, with several gussets now dealt with and alignment started on the replacements.

Localised welded repairs to the brake weighshaft brackets have been made where they had been damaged by a gas axe when NG29 was being ‘flat packed’ ready for containerised transport from Africa to the UK. The outer bracket has been re-installed, although it will require further alignment or line boring before the new weighshaft can be fitted in the future. Unfortunately aligning the inner bracket showed a significant bend in the chassis structural member it is attached to, which means it needs to be replaced. That in itself isn’t a major task, but it has so far proved impossible to secure supplies of the obsolete steel size used when the chassis was constructed in 1910. Various avenues are being pursued, including profile cutting down the modern equivalent and trying to find reclaimed steel in the correct size.

9th October 2025

Some more interesting drawings of NG29’s new draw bar assembly. These are adapted from the original Craven’s drawings incorporating some differences to allow for modern manufacturing considerations and some design aspects from the Ffestiniog Railway ‘Super barn’ carriages.

8th October 2025:

NG29’s brake weighshaft brackets were bent and damaged but fortunately have survived with the carriage. These have been straightened and are ready for reinstallation.

22nd September 2025

Design work continues on NG29’s draw bars. One is missing and the other has been cut through with a gas axe so new ones are being drawn up so replacements can be made.

3rd September 2025

The custom in house made union nuts for the bogie pivot oil pots are done and are absolutely beautiful.

11th August 2025

The bogie oil pots are now installed and union manufacture is underway. Work is progressing well on the corrosion repairs, and the new rivet forge has arrived. Discussions are underway with Boston Lodge regarding the wheel sets and axle boxes.

10th August 2025

The replacement solebar section is installed. A large number of holes still need to be drilled and there is some more trimming to be done to make the modern profile match the original steel.

7th August 2025

The bogie pivot oil pots are now polished and ready to install. A before photo really illustrates the amazing transformation.

The stencils have arrived for the chassis sign writing, along with the new gussets and profiles for the foot board brackets.

6th August 2025

The repair work on NG29’s chassis is moving around systematically so structural strength and dimensional accuracy are not risked unnecessarily. The replacement gussets are expected in the next few days, along with the profiles for the foot board brackets. The first section of five wasted chassis members has been cut out ready for replacement.

03rd August 2025

More progress has been made on the chassis. The first of the heavily corroded gussets has been removed, various corroded fasteners have been replaced. Three of the truss rod locating castings require some level of repair but the fourth is in good condition and has been reinstalled. Two more new body mount brackets have been installed and more large areas that are repaired or don’t require repairhave had either their first or second coat of black paint.

31st July 2025

The new lateral support wear plates and a set of horn guides for the most worn bogie have arrived.

30st July 2025

More painting progress has been made, the first of the body support brackets is on and the second is in progress.

29th July 2025

The channel section has arrived for the repairs to NG29’s chassis.

25th July 2025

Discussions are underway with the Ffestiniog Railway’s draughtsman on the best way to replace the missing and damaged drawbars. The new couplings have been retrieved from storage and test fitted at the end of the chassis that still has most of its parts.

24th July 2025

The bogies pivot oil pots have gone away to be polished ready for reinstallation, and work has begun on replacing the 16 body support brackets. Due to the environment it was designed for the entire body is raised above the chassis on blocks which rest partially on the brackets and partially on the solebars.

21st July 2025

The chassis is now on stands to facilitate repair work. A detailed assessment of the chassis has begun, with more black paint applied where work isn’t needed. The first of the builder’s plates has also been reinstalled.

27th February 2025

Marking out for repair has started on the chassis so the steel can be ordered. Any of the (small!) sections that don’t require repair are being painted black as we go.